Trip / Tally Displacement
Planned-versus-observed trip monitoring · connection-aware string tally · V2.0
Trip-tank displacement path
Pull out of hole · surface
String position and trip tank
pooh · 10 units · current string depth
Cumulative fill comparison
Expected versus observed volume over moved segments
Expected volume
6.416 bbl
Observed volume
Not entered
Expected strokes
64.2 strokes
Moved length
900 ft
Planned tank level
28.58 bbl
Review · not a diagnosis
Trip monitoring snapshot
Observed − expected
Not entered
Metal displacement
6.416 bbl
Closed-end displacement
22.27 bbl
Unfilled pressure reduction
28.4 psi
Explicit geometry · measured volume stays separate
Trip sheet and physical tally
Operation configuration
Tally rows
Enter stands, joints, or assemblies in movement order. Connection geometry is calculated separately.
Row result
Calculation complete
Calculation audit
Expected
6.416 bbl
Observed
—
Joints
30
Strokes
64.2
Calculation observations
Static cylindrical displacement only. Surge/swab, compressibility, ballooning, losses, influx, gas migration, riser motion, sensor lag, transfers, and dynamic trip-tank response are excluded.